Project in numbers:

50,328 m²
Work site area
1,356 pcs.
Quantity of lighting fixtures installed
2017
Project implementation
Mikheyevskiy Mining and Refining Facility is located 250 km away from Chelyabinsk, in the Varna District of the Chelyabinsk Oblast. The Mikheevskoye deposit of porphyry copper ores is one of the largest deposits in Russia. Its erection became the largest project for copper ore extraction and refining in the post-Soviet space. The project was completed in record-breaking time.
01
Design works
02
Electrical installation works
03
Supply lighting equipment
04
Services electrical laboratories

The works were carried out at the following sites:

Crushing (lower light);

Flotation;

Broken ore warehouse;

Critical class further crushing building;

Lime warehouse.

Galleries: №1, 2, 3, 4, 5;

Project achievements:

Philips BY698 lamp with a unique cooling system is used, due to the use of through ribs, dust does not settle on the lamp body. The work was carried out in shifts around the clock, in the winter months the temperature dropped below -30°C, which significantly complicated the installation work.

The BM-ELECTRO team showed high qualifications and was highly appreciated by the Customer's management.

The following equipment was used at this facility: