Services Projects Recommendations Contacts
Mikheyevskiy GOK
Chelyabinsk, 2016 г.

Project Manager:

Danila Sitnikov
Danila Sitnikov
Danila Sitnikov is a project manager, our key employee. He successfully completed projects in most remote areas of the Russian Federation; his favorite cities are Krasnoyarsk, Irkutsk, Vladivostok, Chelyabinsk.

Project in numbers:

7,200 m²
Work site area
112 pcs
Quantity of lighting fixtures installed
2016
Project implementation
Mikheyevskiy Mining and Refining Facility is located 250 km away from Chelyabinsk, in the Varna District of the Chelyabinsk Oblast. Its erection became the largest project for copper ore extraction and refining in the post-Soviet space. The project was completed in record-breaking time.
01
Design works
02
Electrical installation works
03
Supply lighting equipment
04
Services electrical laboratories

The works were carried out at the following sites:

Crushing (upper light)

Project achievements:

Mikheevsky GOK is one of the first BM-ELECTRO projects implemented for the Russian Copper Company (hereinafter - RMK). The implementation of this project gave rise to fruitful cooperation between our team and RMK. Since 2016, BM-ELECTRO has been RMK's system contractor for the implementation of projects in the EO section. Philips equipment has proven itself well at the sites of the Mikheevsky GOK, failure (replacement under warranty) during the first three years of operation did not exceed - 1%. The work on this site was completed two weeks ahead of the deadline set by the contract. In the "Grinding" section, the normalized illumination has been achieved in accordance with the TOR. The qualification of our team's work was highly appreciated, which is reflected in the corresponding letter of recommendation from the Customer, a letter to your attention at the link.

The following equipment was used at this facility: