Project in numbers:

10,000 m²
Work site area
180 pcs.
Quantity of lighting fixtures installed
2016
Project implementation
The Novosibirsk factory is one of the largest beverage bottling enterprises in the region. It is the only enterprise capable of ensuring recommended daily liquid consumption of more than 150 thousand persons all year. It is an important employer in the region where almost 700 persons work from Novosibirsk and its outskirts..
01
Design works
02
Electrical installation works
03
Supply lighting equipment
04
Services electrical laboratories

The works were carried out at the following sites:

Finished products warehouse;

Finished products loading area.

Project achievements:

Our specialists have implemented a project for the installation of lighting equipment in the finished product warehouse and in the finished product loading area. The lamps on this project were provided by the Customer, Coca-Cola HBC Eurasia LLC. The replacement of the lamps was carried out on a one-to-one basis.
During the implementation of the project, the specialists of our team noted the low quality of the lamps of this manufacturer, Sirecled company. In order to achieve the regulatory indicators, the installation of additional lamps was required, which also negatively affected the savings planned by the Customer.