Main building - section of the flotation department
The installation of the overhead lighting system is carried out from a bridge crane. Work on this project was carried out in winter, part of the work took place at night due to the total employment of the bridge crane during the daytime by other contractors. In winter, the air temperature at night reached -35°C to -38°C. Conducting construction and installation works at night in the cold at a height of 30 meters is a difficult and dangerous task that requires maximum concentration and professionalism from installers.
Despite the difficult circumstances, all the work was completed on time.
The quality of the work meets the high level of requirements of the RMK company.