Services Projects Recommendations Contacts
Tominskiy GOK
Chelyabinsk, 2019

Project Manager:

Danila Sitnikov
Danila Sitnikov
Danila Sitnikov is a project manager, our key employee. He successfully completed projects in most remote areas of the Russian Federation; his favorite cities are Krasnoyarsk, Irkutsk, Vladivostok, Chelyabinsk.

Project in numbers:

13,608 m²
Work site area
200 pcs.
Quantity of lighting fixtures installed
2019
Project implementation
Tominskiy Mining and Refining Complex, a refinery with a capacity of 28.0 million tons per year, is a hi-tech enterprise for porphyry copper mining and refining at the Tominskoye Field of the Chelyabinsk Oblast. The project of Tominskiy GOK construction is a part of the Strategy of Non-Ferrous Metallurgy Development in Russia for 2014–2020 and up to 2030.
01
Design works
02
Electrical installation works
03
Supply lighting equipment
04
Services electrical laboratories

The works were carried out at the following sites:

Main building - grinding department

Project achievements:

Tominsky GOK became the second major project of BM-ELECTRO implemented for a Russian Copper Company. The BM-ELECTRO team, which had been working for more than 2.5 years on the Mikheevsky GOK project, was sent to Chelyabinsk in full force and, rolling up its sleeves, set about implementing such a large-scale and ambitious project. The schedule of work was very tight, the work was carried out including in the night shift, it should be noted that in the grinding department the height of the suspension of the lamps is about 30 meters, and now imagine the height of a ten-story house, night, February, the temperature inside -32°C, in such conditions the qualification of installers is very important!

At the end of the project, the management of the Tominsky GOK highly appreciated the professional actions of the BM-ELECTRO team.

The following equipment was used at this facility: