Services Projects Recommendations Contacts
Amur Minerals LLC
Khabarovsk region, Malmyzh, 2023 г.

Project Manager:

Danila Sitnikov
Danila Sitnikov
Danila Sitnikov is a project manager, our key employee. He successfully completed projects in most remote areas of the Russian Federation; his favorite cities are Krasnoyarsk, Irkutsk, Vladivostok, Chelyabinsk.

Project in numbers:

27 864 м²
Work site area
1200 pcs
Quantity of lighting fixtures installed
2023
Project implementation
Amur Minerals LLC (part of the Russian Copper Company Group, RMK) is the operator of the development of the world—class Malmyzhsky copper deposit.
During 2024-2025, RMK plans to build a modern mining and processing plant at the deposit in four stages with a processing capacity of 90 million tons of ore per year.

The best available technologies that will be implemented at the new enterprise will ensure economic efficiency and environmental safety of production.
02
Electrical installation works
03
Supply lighting equipment
04
Services electrical laboratories

The works were carried out at the following sites:

The main building. Lighting of the grinding department sites.

Project achievements:

Energy-efficient Philips LED lamps have been used as part of the enrichment plant construction project.